General view of the site of the under-construction world's highest railway bridge over the Chenab river in Kauri in northern Jammu and Kashmir state. (AFP)

Published
By AFP

Indian engineers are toiling in the Himalayas to build the world's highest railway bridge which is expected to be 35 metres taller than the Eiffel Tower when completed by 2016.

The arch-shaped steel structure is being constructed over the Chenab River to link sections of the spectacular mountainous region of India's northern Jammu and Kashmir state.

Pic: AFP

The bridge is expected to be 359 metres (1,177 feet) high when completed - surpassing the world's current tallest railway bridge over the Beipanjiang River in China's Guizhou province, which stands at 275 metres high.

"It is an engineering marvel. We hope to get this bridge ready by December 2016," a senior Indian Railways official told AFP.

"The design would ensure that it withstands seismic activities and high wind speeds," he said Wednesday.

Pic: AFP

Work on the bridge started in 2002 but safety and feasibility concerns, including the area's strong winds, saw the project halted in 2008 before being green-lighted again two years later.

The estimated cost of the project, which is being handled by Konkan Railway Corporation, a subsidiary of state-owned Indian Railways, is $92 million.

The bridge will connect Baramulla to Jammu in the Himalayan state with a travel time of six-and-a-half hours, almost half the time it currently takes.

Pic: AFP

The main arch is being erected using two cable cranes attached on either side of the river which are secured on enormous steel pylons, according to engineers of the project.

The 1,315-metre long bridge will use up to 25,000 tonnes of steel with some material being transported by helicopters due to the tough terrain, they said.

"One of the biggest challenges involved was constructing the bridge without obstructing the flow of the river," the railways official said.

"Approach roads had to be constructed to reach the foundations of the bridge," he added.