Work on the second phase of the Angsana Resort and Spa Eastern Mangroves project in Abu Dhabi was expected to start in May but the new contractors will most likely be announced in June, said Al Habtoor Leighton.

Meanwhile, the firm has started demobilising from the Angsana Resort project as construction work on phase one is almost complete. "Phase one, involving enabling and foundation, will be ready by end-July," said an official on condition of anonymity. Complete demobilisation from the site will be achieved by mid-August," said Stuart Magee, Tdic Executive Director Project Delivery.

"Piling works are already complete. We are about to award the superstructure package in the next two months. We are on schedule to be fully operational by the first quarter of 2011," said Magee. The Tourism Development and Investment Company's Eastern Mangroves project will involve the construction of a 223-room, five-star hotel with conference facilities, shops and 129 apartments.

The second phase involves the construction of a 148-room hotel, which will be managed by Westin, as well as a conference centre.

The project includes the construction of a resort hotel and spa, stilted water villas, 225 apartments, commercial, retail and support services, interpretive centre and nature trails through mangrove area and a bridge to access to the Mangrove Island. Most of the structures is being constructed on reclaimed land and on piled foundations. The structures are mostly G+5 buildings with one basement level.

"We are following the highest environmental standards when it comes to construction. We have not touched the mangroves. What we have put in is some sheet piling to retain the existing waters and the waters will be flooded into the new channels by December," added Magee.

"The site is more than one-kilometre long. There is a lot of activity and we currently have about 460 men on site. The number will increase as the work progresses," he added.

Meanwhile, Al Habtoor, which was initially scheduled to work on the second phase had to submit three different bids before the project was re-tendered.

Leighton submitted the initial bid early last year for Dh1.8billion on a cost-plus basis. In August 2008, Tdic then asked the contractor to rework on the contract and submit a lumpsum bid, which it did for Dh1.6billion. In December 2008, the contractor was again asked to revise its bid, which it did for Dh1.2billion.

"However, the contractor was soon informed that the developer plans to re-tender the project.

"In the second week of January, Tdic invited contractors to bid for the project and requested submissions within two weeks. The submission date was extended to February 15," said the official.

Sources indicate that although several contractors submitted their bids for the second phase, Nasa Multiplex and Alec are in the lead.

Tdic-Leighton Contracting LLC – was formed in December 2007 to undertake various contracts for Tdic developments. Following the termination of the joint venture, most projects will go in for retendering.

"The economic situation is changing, we are reviewing what makes best sense with each project on taking decisions on an individual basis. The options for developers today have increased," said Magee.

 