The incessant screech and whine of jackhammers and pneumatic drills drowns out the noise of dozens of men, dressed in heavy construction gear, as they yell instructions to each other.

But this deafening racket of construction has defined life for the past 26 months at the Dubai Metro site for the Rashidiya Station.

And, if seeing is believing, then the Dh15.5 billion Dubai Metro suddenly seems very palpable, very certain, very "here" – and ready to roll on September 9 next year.

It is Wednesday morning, and a group of Roads and Transport Authority officials and members of the UAE media are at the site of the Rashidiya station, the starting point for the first guided media tour of Dubai Metro construction sites since work began in April 2006.

From what used to be a family park where parents and children passed their time, the area is being transformed to provide something better – an elevated modern Metro station that will ease the weight of traffic on the emirate's roads.

To keep the RTA's promise, hundreds of workers are racing against the clock to complete the station as planned. Almost 50 per cent of the work is complete. Alongside the station, workers are digging the foundation for a multi-storey car park with space for 28,000 vehicles that will allow Metro users to easily switch between private vehicles and Dubai's new public transport system.

The car park is one of three that will be built for Dubai Metro passengers. The other two buildings will be at Al Qusais Station and Jumeirah Island, with a capacity of 28,000 vehicles each.

But as one begins to absorb the beehive of activity and ponder upon the depth of the job being done, our next stop – Al Rashidiya Main Metro Depot – takes us by awe. A massive steel structure standing on an area of 10,000 square metres, once completed, this will be the heart and brain of the Dubai Metro. It is here that maintenance of all the trains will be done and it will also house the main Rail Operation Centre where the administration offices will be located. It will contain sliding and cleaning facilities, a track-building area, light repair workshops, a general overhaul workshop and train-washing machines.

While taking us around, Adnan Al Hammadi, director of Construction Department at the Rail Agency of the RTA, says the depot will be ready before the operations of Dubai Metro begin in September next year.

The first and biggest phase of the depot, building number one that will contain parking for the trains, will be completed by the end of this year. The depot, just like the Metro stations, is being built using only steel and heat resistant glass, and so far more than 50 per cent of the steel work has been completed.

Our next stop is at what is set to become one of the widest underground Metro stations in the world – the Union Square Station construction site. The daily rush of people that used to be a constant fixture at the former Union Square bus station and its vicinity has completely disappeared.

But beneath this piece of land are hundreds of workers and a host of equipment all in full action, as 60 per cent of the construction work on Union Square station nears completion.

A visitor can only marvel at the amount of effort and expertise that was needed to create a grotto 280 metres long and 50 metres wide and 29 metre beneath the ground. This engineering feat was made possible by the tunnel boring machines named Al Wugeisha.

Anthony Burchell, Project Director for The Engineer, contractors for the Dubai Metro construction work, says the station will have a handing capacity of 20,000 passengers per hour.

The Union Square Station will have two levels. Passengers will descend from the main entrance to a concourse level using elevators and escalators. This will be the main lounge for the station and the tickets counters will be located here. Passengers will then descend to the platform level where they will board the trains. Union Square station is one of only two stations where the Red and Green lines will meet. The other one is BurJuman station.

Burchell further tells us that plans are under way to develop the area above the station into an amusement park. An intercity bus terminal, an elevated link to the proposed ferry station and a taxi stand with a capacity of 50 vehicles would also be developed. Subways would be created to link the station to adjoining areas.

At one end, the station is linked to the tunnel on the Red Line that goes under the Dubai Creek and on the other to the tunnel leading to Al Rigga underground station. A walk from the station's platform level through the 948 metres concrete tunnel leads us to the Al Rigga Station where work is also at full swing. The fully lit tunnel is 12 metres below the ground and workers are laying the foundations of the tracks.

A total of 2.25 million cubic metres of concrete and 400,000 tonnes of steel would be used for the construction of both the Red and Green lines. A total of 24,000 people are currently working on the project.

 

World record

Once completed, Dubai Metro will be the world's longest automated railway system to be constructed in one phase.

The 52.9km Red Line is almost 70 per cent complete and is scheduled to commence operations on September 9, 2009, while the 23km Green Line is 27 per cent complete and will operate from March 2010. The Metro will operate from 5.30am until 12.30am with trains travelling at a 90kph.