Schön Properties and its infrastructure design consultant, Sinergo, disclosed that the infrastructure design for the Dubai Lagoons is developing in tandem with the construction progress of the project.
Sinergo won the Dh1.5 million infrastructure design contract. Other contractors on the project include Bin Sabt Building Contracting Company, Belhasa Contracting and Engineering Company, Commodore Contracting and project consultants, Mazaya.
The developer is also shortlisting companies specialised in infrastructure works who will be invited to bid once the design is completed. Building will be done in stages, with three months allocated for each stage. Work is on for zones 2 and 4 while structural works for zone 1 are completed. The structures for zone 3 are set for completion by end 2010 and for zones 2 and 4, within 18 months.