Remobilisation has started on the villas in the Acacia Avenues project in Dubai, according to a senior official close to the project. However, work has stopped on the Olgana and Hiliana Towers.

"Remobilisation has started on the villas as we speak. The focus is to get the villas complete with the funding that they received in Kuwait. We were not involved with the villas but only with the towers. The two buildings won't probably start until next year," said Luc Theberge, Vice-President for Middle East at EllisDon.

"We were hired to come in at a late stage around November 2008 and worked up until February. Then due to the crisis, they shut the project down. The contractors stopped work in February. Our role as project managers was to manage the contractors and consultants but that has stopped." He told Emirates Business that EllisDon will come back on the project should and when "market conditions change".

Acacia Avenues is the first freehold project in Jumeirah and was launched by Abyaar in 2007. It comprises 52 villas and six towers extending on an area of 94, 000 square metres, close to Knowledge Village in Jumeirah. The first phase of the project also features two towers. Olgana Tower is a 38-floor building and Hilliana Tower, a 45-floor building.

In February, Abyaar Real Estate Development Company from Kuwait denied media reports on the suspension of the construction works in its Dh2 billion Acacia Avenues project on account of financial crisis.

Marzouq Al Rashdan, Abyaar Vice-President and Managing Director, then said: "We do not usually reply to rumours, but the difficult economic conditions experienced worldwide have necessitated this denial, ensuring that correct and accurate information is communicated to all shareholders and clients".

He added that it had "announced last week that phase one of the project will be delivered during 2009".

By the end of March, the developer clarified that it was renegotiating its contracting agreement with Al Habtoor Engineering Enterprises, concerning the construction of two residential towers. Abyaar's CEO Hussain Al Basri said "most real estate developers in the region are currently reconsidering their contracting agreements, ensuring the reduction of the cost margin for the contracting agreements of projects under construction" and that "the contracting agreement signed with Al Habtoor is no exception to this rule". Negotiations are under way with contracting companies to participate in the tender intended to be launched for executing the project, including Al Habtoor, he added. In June, Hesham Abdul Wahab Al Obeid, Abyaar Chairman of the board of directors, said in a statement that the developer had entered into a new financing deal with the Bank of Kuwait and The Middle East – estimated at about KD18 million (Dh231m), with the agreed tenor being up to five years).

"The primary objective behind the new financing deal is the completion of the company's projects under construction, and the rescheduling of its local and foreign financial obligations, whether due or not yet due," said Al Obeid. In July and September, in separate statements he reiterated that the "main objective is to complete the projects under construction, comprising Acacia Villas located within Acacia Avenues and Pier 8 Tower located in Dubai Marina area. Therefore, the new financing transactions will be currently directed to those projects."

However, when repeatedly contacted by e-mail and telephone, the developer refused to update on the renegotiations with Al Habtoor and or on the timeline of the project.

 