Saudi-based contractors said state oil giant Saudi Aramco has set December 5 as the new deadline for bids to build an estimated $200 million (Dh735m) fuel distribution plant near Riyadh.

The plant located in Wasea, would have the capacity to handle 185,000 barrels per day (bpd) of oil.

The plant is a wholesale receiving and distributing facility for oil refined fuel products. It includes storage tanks, warehouses and truck-loading facilities.

"The bidding deadline was too short, luckily we got the confirmation last week [that it has been extended]," said one contractor.

Three Saudi-based contractors said they did not have enough time to prepare bids as Aramco was asking for more work to be done during the tender process.

Contractors had originally been asked to bid for the project by mid-November. The project was slated for completion by the end of November 2011. It is not clear for how long the extension will delay the completion of the project.

One contractor said the one-month extension is unlikely to affect the completion target.

Aramco is overhauling and expanding domestic distribution facilities to meet rapidly-rising domestic demand.

Contractors could not confirm if there will be a new extension.

"They will keep December 5 as the deadline for bids as they are in need to meet demand from the central region," said one contractor.

Aramco has 20 fuel distribution plants, called bulk plants in Saudi Arabia, the company shows in its 2008 annual report.

It recently awarded the local company MS Al Suwaidi Industrial Services a contract for the upgrade of 14 bulk plants in several regions in the kingdom to raise the storage capacity for petrol, diesel and fuel oil.

Distillation unit to be shut

Saudi Aramco was expected to shut the crude distillation unit at its Ras Tanura refinery in mid-December for planned maintenance, industry sources said.

The 325,000 barrels per day (bpd) crude processing unit was expected to be offline between 30 and 50 days, they said. "The unit will be shut for 50 days, this is maintenance which is already part of their schedule, so minimal disruptions," said a Middle East-based trader.

The 550,000 bpd refinery located at Ras Tanura is the largest refinery in the kingdom, which includes the world's largest offshore oil facility with a capacity to load between 5.5 million and six million bpd of oil. Aramco has yet to make a decision to take the problematic 44,000bpd hydrocracker offline, after it was shut for almost five months earlier this year.

 