President His Highness Sheikh Khalifa bin Zayed Al Nahyan has ordered provision 2.5 million gallon per day of water supplies to Al Madam area in Sharjah from the main Fujairah-Al Ain water pipeline, which belongs to the Abu Dhabi Water and Electricity Authority (Adwea).
According to Federal Electricity and Water Authority (Fewa) estimations, there are 900 residential units in Al Madam, distributed over 42 local districts and inhabited by 10,000 people.
Fewa was instructed to establish water distribution networks in all districts of Al Madam. The network, to be built at a total cost of Dh180 million, will be ready in two years.
The project also entails construction of a 4 million gallon water tank, 300-400 millimeter and 80 -km water transport lines and 150km distribution lines.
The project will see Adwea completing provision of water supplies to all areas in the central region. The authority is already supplying water to Al Fili, Al Dhaid, Kadra, Al Huwailat, Maliha, Hamda, Falaj Al Mualla, Idhn and all villages there.